How to lay double brick walls
🧱 Laying Double Brick Walls — Professional Trade Guide Double brick construction involves building two separate masonry leaves with a cavity between them, tied together with corrosion-resistant wall ties to provide structural stability, moisture management and thermal performance. In Australia
- Skill level
- Advanced
- Time
- 2–5 days depending on wall length, height, openings, articulation joints and site access
- Trade
- Building & Construction
- Updated
- 4 November 2026
Tools you will need
- Brick trowels, including 280 mm
- Brick bolster and club hammer
- Bricklayers line pins, line blocks and mason’s string line
- Spirit levels: 600 mm, 1200 mm and 1800 mm
- Aluminium straightedge 1800 mm
- Gauge rod marked to course heights
- Tape measure 5 m and 8 m
- Builder’s square and folding rule
- Joint raker and brick jointer/irons
- Spot board or mortar board
What is double brick construction in Australia?
🧱 Laying Double Brick Walls — Professional Trade Guide
Double brick construction involves building two separate masonry leaves with a cavity between them, tied together with corrosion-resistant wall ties to provide structural stability, moisture management and thermal performance. In Australian practice, correct set-out, cavity control, tie placement, damp-proofing and sequencing are critical to comply with AS 3700 Masonry Structures, NCC requirements and relevant state-based building controls.
What skill level is required for laying double brick walls?
Advanced — Estimated time: 2–5 days depending on wall length, height, openings, articulation joints and site access
What tools are essential for laying double brick walls?
🔧 Tools Required
What materials are needed for double brick wall construction?
Safety Requirements
⚠️ Safety
Step-by-Step Guide
Step 1: Set out the wall and confirm structural details
1️⃣ Set-Out and Documentation Check
Confirm all drawings, engineering details, footing dimensions, wall thicknesses, cavity widths, articulation joints, tie schedules, openings and lintel sizes before laying begins. Double brick walls are commonly formed from two 110 mm leaves with a cavity typically in the order of 40 mm–60 mm, but the actual cavity must match the project documents and exposure classification.
Transfer datum levels from the slab or footing and mark all corners, returns, piers, openings and control joints. Check that footing width and bearing are suitable for the total wall thickness and loads. On reactive sites or articulated masonry systems, confirm joint spacing and movement detailing exactly to the engineer’s and manufacturer’s requirements.
Use a gauge rod to establish course heights, allowing for brick size plus mortar bed. Check modular set-out at openings to minimise awkward cuts and maintain bond.
Step 2: Prepare the base and install damp-proofing
2️⃣ Base Preparation and DPC Installation
Ensure the slab rebate or footing surface is clean, level and free from laitance, mud or loose material. Any significant level variation should be corrected before bricklaying starts; do not attempt to absorb major discrepancies in bed joints.
Install the damp-proof course and base flashings as detailed. In cavity masonry, the flashing must direct any moisture in the cavity toward the external face and weepholes. Keep the DPC correctly lapped, unpunctured where possible and turned up/down in accordance with the detail.
Mark the inside and outside leaf positions clearly so the cavity remains consistent along the full wall run.
Step 3: Mix mortar to suit the brickwork application
3️⃣ Mortar Selection and Mixing
Use a mortar compatible with the brick type, exposure conditions and specification. For site mixes, a general bricklaying mortar may vary depending on exposure and workability requirements; follow the project specification or mortar manufacturer guidance rather than using a one-size-fits-all mix.
Where a general-purpose mix is nominated for associated works, a common reference is 1:2:3. For higher structural applications where specified, a mix such as 1:1.5:2.5 may be used, but structural masonry mortar should always align with engineering and specification requirements.
Mix only enough mortar to maintain consistent workability without excessive retempering. Mortar should be plastic, cohesive and able to support brick units without slumping. Keep colour and consistency uniform across visible facework.
Step 4: Build and plumb the leads
4️⃣ Corner Leads and Initial Courses
Build corner leads for both leaves first, typically 4–6 courses high, checking plumb, level and gauge continuously. The leads establish the wall’s line, bond and cavity width, so accuracy here controls the whole job.
Lay the first course carefully on a full, even bed. Fully bed perpends and maintain consistent joint thickness to specification, commonly around 10 mm unless project requirements differ. Use the gauge rod at every course and regularly measure cavity width between leaves.
For face brickwork, select bricks to maintain colour blend and avoid clustering of shade variations.
Step 5: Run both leaves up together in sequence
5️⃣ Sequencing the Inner and Outer Leaves
Run the inner and outer leaves progressively together rather than completing one leaf too far ahead of the other. Keeping the leaves within a manageable height difference improves tie installation, cavity cleaning and line control.
Stretch lines between leads for each leaf and lay to the line, not by eye. Maintain full bed joints and solid perpends unless a specific joint profile or drainage detail requires otherwise. Frequently check for:
Stretcher bond is the most common arrangement in modern double brick construction, though project documents may call for alternative bond treatments in visible facework.
Step 6: Install wall ties at the correct spacing
6️⃣ Wall Tie Placement and Fixing
Install wall ties to the type, material and spacing nominated in the drawings and AS 3700 exposure requirements. In Australian practice, ties are commonly galvanised or stainless steel depending on corrosion environment, with stainless often preferred in coastal or severe exposure zones.
Ties should be laid with a slight fall toward the external leaf where required by the proprietary system so moisture is not directed inward. Place ties as work proceeds, ensuring embedment into both mortar joints is adequate and that mortar fully surrounds the tie.
Increase tie density at:
Do not allow mortar droppings to bridge the cavity or sit heavily on ties, as this compromises drainage and can transfer moisture.
Step 7: Maintain a clean and unobstructed cavity
7️⃣ Cavity Control and Moisture Management
Keep the cavity free of mortar dags and debris at all times. Use cavity battens/boards to catch droppings as the wall rises, removing and cleaning them progressively. A blocked cavity can lead to moisture tracking across to the internal leaf.
Install flashings, weepholes and vents exactly as detailed. Weepholes are generally placed at the base of the outer leaf and above openings where flashing is present, at centres nominated by the documentation or manufacturer. Ensure the weephole path is not blocked by mortar.
This stage is critical in exposed Australian conditions, especially in high rainfall or coastal zones.
Step 8: Form openings, install lintels and continue bond
8️⃣ Openings, Lintels and Returns
Set out window and door openings carefully to maintain coursing and minimise cuts. Install lintels level, with correct end bearing to the engineer’s or manufacturer’s detail. Ensure cavity flashings above lintels discharge to the external face via weepholes.
Maintain tie placement around reveals and openings, usually at closer centres as specified. Check jamb plumb and sill levels before proceeding above openings.
At returns and junctions, preserve the specified bond and tie arrangement. Any deviation at returns can create cracking, poor alignment and structural non-compliance.
Step 9: Install articulation and movement joints
9️⃣ Movement Control
Double brickwork requires movement joints in the locations nominated on the plans and in accordance with articulated masonry principles. Install articulation joints plumb, full height and clear of mortar bridging.
Use approved compressible filler, backing rod and sealant as specified. Ties crossing movement joints must be the correct debonded or movement-capable type where required. Do not hard-pack articulation joints with mortar.
Failure to provide proper movement accommodation is a common cause of masonry cracking on Australian sites, particularly on reactive soils.
Step 10: Finish joints and clean down correctly
🔟 Joint Finishing and Facework Presentation
Tool joints at the correct time once the mortar has thumbprint firmness. Common external finishes include ironed/concave joints for improved weather resistance. Keep joint profile uniform over the full wall area.
Brush off loose mortar as you go. Avoid smearing face bricks with wet mortar, especially on textured or porous units. Use approved cleaning methods only after mortar has cured sufficiently, and always test brick cleaner in an inconspicuous area first.
Check the final wall for:
Common Mistakes to Avoid
Pro Tips
💡 Use a dedicated gauge rod for the exact brick being laid on the project. Small dimensional variations between manufacturers can throw out head heights quickly.
💡 Keep both leaves within a few courses of each other. This improves productivity, tie accuracy and cavity cleanliness.
💡 In facework, blend bricks from at least 3–4 packs at once to avoid colour banding.
💡 Use cavity boards from the first course upward rather than trying to clean hardened droppings later.
💡 In coastal and high-exposure environments, stainless steel ties and accessories often save call-backs and durability issues even where galvanised products may be minimally acceptable.
💡 For large projects, hire rather than purchase masonry scaffold components, brick saws and mixers unless utilisation rates justify ownership. For occasional or short-duration work, hire is usually more economical and reduces maintenance/compliance burden.
Recommended Tools
🔧 Recommended Tools
Frequently asked questions
- What is involved in lay double brick walls?
- 🧱 Laying Double Brick Walls — Professional Trade Guide Double brick construction involves building two separate masonry leaves with a cavity between them, tied together with corrosion-resistant wall ties to provide structural stability, moisture management and thermal performance. In Australia
- What skill level do I need for lay double brick walls?
- Advanced — Estimated time: 2–5 days depending on wall length, height, openings, articulation joints and site access
- What are common mistakes when lay double brick walls?
- 1. Allowing the cavity to fill with mortar droppings, creating moisture bridges and blocked drainage paths. 2. Running one leaf too far ahead of the other, making tie installation and cavity inspection difficult. 3. Incorrect wall tie spacing, wrong tie type for exposure zone, or poor embedment into mortar joints. 4. Failing to install flashings and weepholes correctly at the base of walls and abo
- What tools do I need for lay double brick walls?
- This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
- What is the Australian standard for masonry structures?
- The primary Australian standard for masonry structures, including double brick walls, is AS 3700 Masonry Structures. This standard outlines requirements for design, construction, and materials to ensure structural integrity and durability. It works in conjunction with the National Construction Code (NCC) for compliance.
- How do wall ties contribute to double brick stability?
- Wall ties are crucial for connecting the inner and outer leaves of a double brick wall, providing structural stability and preventing differential movement. According to AS/NZS 2699.1:2020, they must be corrosion-resistant, correctly spaced, and adequately embedded in mortar to transfer loads and maintain cavity width.
- Why is cavity control important in double brick construction?
- Cavity control is vital for moisture management and thermal performance in double brick walls. A clear cavity, typically 50-75mm, prevents moisture bridging from the outer leaf to the inner leaf and allows for insulation installation, enhancing the wall's energy efficiency and preventing dampness issues.