How to build a timber privacy screen for an outdoor area

This guide covers a freestanding timber privacy screen measuring approximately 2400 mm wide × 1800 mm high, with horizontal slats and three posts. It is designed as a practical DIY project, but the posts and footings must be checked for local wind, soil and site conditions before construction.

Quick answer

Build a timber privacy screen by checking approvals and underground services, setting posts in site-designed footings, allowing concrete to gain the specified strength, then fixing evenly spaced exterior timber slats. For a 2400 mm-wide screen, 22 slats measuring 70 mm wide with 10 mm gaps form a 1750 mm-high panel.

Skill level
⏱️ Skill Level: Intermediate
Time
2 working days, plus concrete curing time. A beginner with basic carpentry skills can complete the work with a helper and appropriate footing advice.
Trade
Carpentry & Joinery
Updated
14 November 2026

Tools you will need

  • Post
  • Spirit level, at least 1200 mm long, and tape measure
  • Circular saw or mitre saw, with a sharp timber
  • Stringline, clamps and shovel
  • Concrete

🪚 How to Build a Timber Privacy Screen

How do you build a freestanding timber privacy screen?

This guide covers a freestanding timber privacy screen measuring approximately 2400 mm wide × 1800 mm high, with horizontal slats and three posts. It is designed as a practical DIY project, but the posts and footings must be checked for local wind, soil and site conditions before construction.

The example uses 70 × 19 mm hardwood slats with 10 mm gaps. You can adjust the appearance, but do not assume the same post and footing details will suit a larger or more exposed screen.

What skills and time do you need to build a timber privacy screen?

⏱️ Skill Level: Intermediate — approximately 2 working days, plus concrete curing time. A beginner with basic carpentry skills can complete the work with a helper and appropriate footing advice.

What tools do you need to build a timber privacy screen?

Post-hole digger or powered auger, suitable for the specified footing diameter
Spirit level, at least 1200 mm long, and tape measure
Circular saw or mitre saw, with a sharp timber-cutting blade
Cordless drill/driver, with drill bits and a countersink bit
Stringline, clamps and shovel
Concrete-mixing equipment or access to a suitable ready-mix delivery

What timber, posts and fixings do you need for an outdoor privacy screen?

🪵 Materials

For the 2400 × 1800 mm example:

3 × 90 × 90 mm H4 treated pine posts, approximately 2700 mm long. Confirm post length, embedment and footing details for the site before purchasing.
22 × 70 × 19 mm hardwood slats, each 2400 mm long, suitable for external use. Select durable species such as merbau or spotted gum, or another appropriately durable exterior timber.
Approximately 150 × 8-gauge, 50 mm stainless-steel screws, subject to the slat manufacturer’s fixing recommendations. Use 316 stainless steel in coastal or other highly corrosive environments.
Exterior timber oil or coating compatible with the selected species—approximately 2 L, subject to product coverage and number of coats.
Temporary bracing timber, such as 70 × 35 mm pine, and suitable temporary screws or stakes.
Concrete for the designed footings. As an illustrative estimate only, three cylindrical holes approximately 450 mm diameter × 900 mm deep contain about 0.43 m³ before allowing for the posts. This may require roughly 45–50 × 20 kg bags, depending on bag yield and wastage.

💡 Pro tip: Footing dimensions above are for estimating only, not a universal design. Wind exposure, soil, screen porosity and local requirements can substantially change the footing and post sizes.

Safety Requirements

⚠️ Safety

Wear safety glasses, hearing protection, sturdy footwear and gloves. Use suitable respiratory protection when cutting treated pine or generating timber dust.
Contact Before You Dig Australia before excavating and locate underground services. Follow the service owner’s instructions and any state or territory excavation requirements.
Check local council and state or territory rules for screen height, setbacks, boundary fences and permits before starting. Obtain the neighbour’s agreement where required for boundary work.
Have a suitably qualified professional assess the screen and footings where wind exposure, poor soil, retaining walls, deck attachments or other site conditions make the design uncertain. AS/NZS 1170.2 is relevant to wind actions; AS 1684 applies where associated residential timber-framing work is involved.
Do not attach the screen to a deck, house, balustrade or retaining wall without confirming that the existing structure and connections can carry the additional wind load.
If the screen is near a pool, check that it does not create a climbable surface or compromise the pool barrier under AS 1926.1 and applicable state or territory requirements.
In bushfire-prone areas, check applicable local rules and AS 3959 requirements before choosing materials and locating the screen.

Step-by-Step Guide

Step 1: 1️⃣ Plan the position and layout

Mark out the screen at 2400 mm wide and 1800 mm above finished ground level. Confirm the boundary, underground services, clearance to structures and any required approvals.

For this example, the outside faces of the two end posts align with the ends of the 2400 mm slats. Centre the third post between them. Check the chosen position provides the desired privacy without blocking access or creating a drainage problem.

💡 Pro tip: Temporarily mark the screen outline with stakes and string. View it from both the outdoor area and neighbouring sightlines before committing to the holes.

Step 2: 2️⃣ Confirm the post and footing design

Arrange for the post size, footing diameter, depth and embedment to be assessed for the site. A privacy screen can attract substantial wind load, even when gaps are present between slats.

Use the 90 × 90 mm H4 posts and indicative footing dimensions in this guide only if they are confirmed as suitable. Check the design specifies how the posts are positioned in the concrete, including any required bottom cover.

Step 3: 3️⃣ Set out and dig the holes

Run a stringline along the intended post line. Mark the two end-post positions and the centre post, then excavate the holes to the approved diameter and depth.

Keep the hole bottoms on firm, undisturbed ground unless the footing design specifies otherwise. Remove loose spoil and confirm each hole is correctly positioned before placing the posts.

Step 4: 4️⃣ Install and brace the posts

Place each post in its footing according to the approved detail. Set the outside faces of the end posts 2400 mm apart, with the centre post midway between them.

Check that:

The posts are plumb in both directions.
Their front faces sit on the same stringline.
The finished post tops will be at 1800 mm above ground.
The specified embedment and concrete cover are maintained.

Brace the posts securely so they cannot move during the pour.

Step 5: 5️⃣ Concrete the posts

Mix and place the concrete to the product instructions and footing design. Compact it carefully around each post without disturbing the alignment.

Finish the concrete at the top so water drains away from the timber. Recheck the post positions and plumb while the concrete is still workable.

Leave the braces in place and allow the concrete to cure as directed by the concrete manufacturer and footing designer before installing the slats or exposing the screen to load. Concrete generally develops its specified strength over approximately 28 days; do not assume it is ready for full loading immediately.

Step 6: 6️⃣ Prepare the slats

Check the 22 slats for straightness, damage and consistent length. Cut them to 2400 mm if required, then lightly sand sharp edges and remove machining dust.

Apply the selected exterior coating to all faces and cut ends as directed by the coating manufacturer. Some hardwoods require weathering or preparation before coating—follow the specific product instructions.

💡 Pro tip: Coat the backs and ends before installation, while they are easy to reach. Merbau can release tannins that stain adjacent paving and finishes, particularly when new.

Step 7: 7️⃣ Mark the slat positions

Starting 50 mm above finished ground level, mark the position of the bottom slat. For the example layout, install 22 slats at 70 mm high with 21 gaps of 10 mm:

Slat coverage: 22 × 70 mm = 1540 mm
Gaps: 21 × 10 mm = 210 mm
Total screen infill height: 1750 mm

With the bottom slat 50 mm above ground, the top of the upper slat aligns with the 1800 mm post height. Check actual timber widths before fixing and adjust the layout if required.

Step 8: 8️⃣ Fix the slats

Clamp the bottom slat across the front faces of the posts and check it is level. Predrill the hardwood and fix it to each post with two stainless-steel screws per post, keeping the fixings appropriately spaced from the slat edges and ends.

Use 10 mm spacers between slats and work upwards. Check level regularly rather than relying on the spacers alone. The centre post supports each slat and helps reduce movement.

Step 9: 9️⃣ Inspect and finish

Remove the temporary braces once the concrete has cured sufficiently. Check every fixing, trim or finish post tops as appropriate, and apply any remaining coating in accordance with the manufacturer’s directions.

Clean the area and dispose of offcuts and treated-timber waste according to local requirements. Do not burn treated timber.

Common Mistakes to Avoid

1.Undersizing the footings: A screen can act as a sail in strong winds. Use a site-appropriate design.
2.Skipping service checks: Underground power, gas, water and communications may be present even in established gardens.
3.Fixing slats before the concrete is ready: Movement can leave posts out of plumb or compromise the footing.
4.Using unsuitable fixings: Ordinary indoor screws can corrode outdoors; select stainless steel appropriate to the exposure.
5.Assuming timber is perfectly uniform: Measure actual slat widths and check the layout before fixing all boards.

Pro Tips

💡 Use a pair of identical 10 mm spacers to keep gaps consistent, but check the slats with a level as you progress.

💡 Predrill hardwood slats to reduce splitting, especially near the ends.

💡 Choose straight, dry slats and store them flat before installation to reduce distortion.

💡 Inspect the coating and fixings annually, and maintain the finish according to the product manufacturer’s recommendations.

Recommended Tools

🔧 Recommended Tools

Cordless drill/driver with countersink bit — for clean pilot holes and controlled screw installation.
1200 mm spirit level — for checking posts and slats accurately.
Mitre saw with a fine-tooth timber blade — for repeatable, neat slat cuts.
Post-hole digger or hire auger — for excavating the specified footings efficiently.

Frequently asked questions

What is involved in build a timber privacy screen for an outdoor area?
This guide covers a freestanding timber privacy screen measuring approximately 2400 mm wide × 1800 mm high, with horizontal slats and three posts. It is designed as a practical DIY project, but the posts and footings must be checked for local wind, soil and site conditions before construction.
What skill level do I need for build a timber privacy screen for an outdoor area?
⏱️ Skill Level: Intermediate — approximately 2 working days, plus concrete curing time. A beginner with basic carpentry skills can complete the work with a helper and appropriate footing advice.
What are common mistakes when build a timber privacy screen for an outdoor area?
1. Undersizing the footings: A screen can act as a sail in strong winds. Use a site-appropriate design. 2. Skipping service checks: Underground power, gas, water and communications may be present even in established gardens. 3. Fixing slats before the concrete is ready: Movement can leave posts out of plumb or compromise the footing. 4. Using unsuitable fixings: Ordinary indoor scr
What tools do I need for build a timber privacy screen for an outdoor area?
This guide includes a comprehensive tools list. Key carpentry & joinery tools are detailed in the Tools Required section.
What Australian Standards apply to a timber privacy screen?
Relevant Australian Standards include AS/NZS 1170.2:2021 for wind actions, AS 1720.1:2010 for timber structural design and AS/NZS 1604.1:2021 for preservative-treated timber. They address different aspects of the work rather than providing one universal privacy-screen design. Confirm applicable editions, amendments, approval conditions and site-specific design requirements with the relevant building authority or designer.
How deep should timber privacy screen posts be?
Timber privacy screen posts need an embedment depth and footing size determined for the screen height, wind exposure, soil and structural arrangement. There is no single safe depth for every Australian site. The example’s 2700 mm posts do not establish an approved embedment depth; obtain suitable footing details before ordering posts or excavating.
Do you need council approval for a timber privacy screen in Australia?
A timber privacy screen may need planning or building approval, depending on the state or territory, council, location, height and construction. A height of 1800 mm does not automatically make a screen exempt nationwide. Check the relevant approval pathway before construction, particularly near boundaries, swimming pools, easements, heritage places or bushfire-prone land.
How many timber slats do you need for an 1800 mm privacy screen?
Twenty-two slats measuring 70 mm wide, separated by twenty-one 10 mm gaps, form a 1750 mm-high slatted panel. An overall height of 1800 mm therefore leaves 50 mm for clearance or another specified allowance. Set out the actual timber dimensions before fixing, and distinguish overall screen height from the height of the slatted panel.
What checks are needed before digging privacy screen post holes?
Check underground service information and establish service locations before digging privacy screen post holes. Before You Dig Australia supplies information from participating asset owners, but plans alone do not confirm exact positions or cover every private service. Follow asset-owner instructions, use competent locating assistance where needed, and assess safe excavation methods before using an auger.

Written by Chippy, the Carpentry & Joinery specialist at Aus.Tools.