How to frame a timber deck substructure

πŸͺš Framing a Timber Deck Substructure A properly framed deck substructure is the backbone of a durable, compliant and straight-finished deck. For Australian residential work, the critical requirements are accurate set-out, correct footing and stump installation, appropriate bearer and joist si

Skill level
Intermediate to Advanced
Time
1-3 days depending on deck size, footing type, access and site conditions
Trade
Carpentry & Joinery
Updated
4 November 2026

Tools you will need

  • Circular saw with timber framing blade
  • Impact driver and 18V drill/driver kit
  • Clamps for holding bearers and joists during fixing
  • Chalk line for joist and bearer marking
  • Moisture meter where hardwood framing is being installed
  • PPE: safety glasses, hearing protection, gloves, steel

What is involved in framing a timber deck substructure?

πŸͺš Framing a Timber Deck Substructure

A properly framed deck substructure is the backbone of a durable, compliant and straight-finished deck. For Australian residential work, the critical requirements are accurate set-out, correct footing and stump installation, appropriate bearer and joist sizing, and compliant fixing methods in line with AS 1684 Residential Timber-Framed Construction and relevant local council or engineer requirements.

This guide covers the standard process for setting out and constructing a timber deck subframe for typical residential applications, including ground-level and raised decks. It is written for trade professionals who need a practical, site-ready sequence using common Australian materials, hardware and framing methods.

What skill level is required to frame a timber deck substructure?

Intermediate to Advanced β€” Estimated time: 1-3 days depending on deck size, footing type, access and site conditions

What tools are essential for framing a timber deck substructure?

Rotary laser level or dumpy level with staff for setting datum and checking stump heights
String line, line level and batter boards/profiles for accurate set-out
Tape measure minimum 8 m, framing square and speed square
Post hole shovel or auger suitable for footing excavation
Circular saw with timber framing blade
Reciprocating saw for trimming posts/stumps where required
Impact driver and 18V drill/driver kit
Socket set or spanner set for structural bolts and hardware
Clamps for holding bearers and joists during fixing
Nail gun or framing hammer where permitted by specification
Chalk line for joist and bearer marking
Moisture meter where hardwood framing is being installed
PPE: safety glasses, hearing protection, gloves, steel-cap boots, dust mask

What materials are needed for a timber deck substructure?

πŸͺ΅ Materials

H4 treated pine posts/stumps sized to engineering and span requirements, commonly 90x90, 100x100 or 125x125
H3 treated pine bearers such as 140x45, 190x45 or built-up members as specified
H3 treated pine joists such as 90x45, 140x45 or 190x45 depending on span and decking load
H3 treated pine rim joists/boundary joists to match joist depth
Galvanised or stainless steel post supports, stirrups or bolt-down brackets as required for exposure class
Hot-dip galvanised M12 bolts, nuts and washers for bearer-to-post connections
Joist hangers, framing anchors or triple grips where specified
Structural screws or hot-dip galvanised nails to suit framing hardware
Concrete for footings, typically 20 MPa minimum unless engineer specifies otherwise
Ant caps where required by local practice or specification
DPC or isolation barrier between dissimilar materials where needed
Temporary bracing timber, typically 90x35 or 90x45
Galvanised angle bracing or timber bracing for lateral restraint if required
Packers/shims rated for structural use only where approved
String line pegs and profile boards
Termite management components where required by state regulations and NCC provisions

Safety Requirements

⚠️ Safety

Wear PPE at all times: safety glasses, hearing protection, steel-cap boots, gloves and respiratory protection when cutting treated timber.
Follow safe manual handling practices when lifting 190x45 or larger members, particularly hardwood and wet treated pine.
Confirm all underground services before digging footings using local service location procedures.
Ensure temporary stability of posts, bearers and partially framed decks during construction.
Use fall protection, edge protection or compliant access systems where deck framing is elevated.
Treated pine cutting and drilling should be completed in well-ventilated areas, with all cut ends resealed using a suitable timber preservative treatment.
Check state-specific requirements for balustrade loads, termite protection, bushfire zones and structural certification.
For structural deck framing attached to an existing dwelling, confirm flashing, ledger fixing design and compliance with the NCC and manufacturer specifications.
Where specialised tools exceed $300, review current EOFY instant asset write-off eligibility with your accountant if purchasing for business use.

Step-by-Step Guide

Step 1: Establish the deck set-out and datum

1️⃣ Set out the footprint

Mark the overall deck size from approved plans, boundary offsets and finished floor relationships. Establish profile boards clear of the excavation zone and run string lines to define the external faces of the deck.

Transfer a consistent datum using a rotary laser level or dumpy level. From that datum, determine the finished deck height, bearer underside levels, joist top levels and footing depths.

Check the deck for square by comparing diagonals. For larger decks, break the frame into bays and confirm each section remains square before excavation begins.

πŸ’‘ A reliable set-out at this stage prevents cumulative errors when lining up posts, bearer centrelines and joist spacing.

Step 2: Confirm spans, member sizes and structural layout

2️⃣ Check the framing design

Before cutting timber, confirm bearer spans, joist spans, cantilevers and post spacings against the approved design, span tables and AS 1684 Residential Timber-Framed Construction. If the deck is engineered, follow the engineering documentation ahead of generic span tables.

Determine:

Joist direction
Bearer lines
Post/stump locations
Rim joist arrangement
Any doubled members under heavy point loads such as stairs, outdoor kitchens or spa surrounds

Mark all footing centres from string lines. Typical framing members may include 140x45 or 190x45 bearers and 90x45 or 140x45 joists, but final selection must match span, species, treatment class and imposed loads.

πŸ’‘ Do not assume standard spans for hardwood and treated pine are interchangeable; species and stress grade matter.

Step 3: Excavate and pour footings

3️⃣ Install footings to correct depth and size

Excavate footings to the required diameter and depth based on engineering, soil classification and local authority requirements. Ensure founding conditions are adequate and free of loose material.

Place concrete footings and install:

Cast-in stirrups, or
Galvanised post supports, or
Direct-embedded treated posts where permitted

Recheck all footing positions from the string lines before concrete sets. Maintain consistent centreline accuracy, especially where multiple bearer rows are involved.

Where the deck adjoins a dwelling, ensure finished excavation and footing placement do not compromise adjacent foundations, drainage or damp-proofing.

πŸ’‘ On sloping sites, set all footing heights from laser, not by eye. Minor footing height variation quickly translates into major bearer packing issues.

Step 4: Install and brace posts or stumps

4️⃣ Stand posts and set heights

Install the posts/stumps plumb and temporarily brace them in both directions. Common post sizes include 90x90, 100x100 and 125x125, depending on load and height.

Mark cut heights from your established datum, allowing for:

Bearer depth
Joist depth
Decking thickness
Required fall or step-down details

Trim posts accurately and treat all cut ends with a preservative resealer suitable for treated timber. If using stirrups or brackets, ensure fixings are the correct type and corrosion resistance for the exposure environment, particularly in coastal areas.

Check alignment along each bearer line before final tightening or fixing.

Step 5: Fix bearers to posts

5️⃣ Install bearers straight and level

Fix bearers to the posts using the nominated structural connection, typically M12 hot-dip galvanised bolts with washers, or proprietary structural brackets. Built-up bearers should be fixed in accordance with manufacturer or engineering details.

Set the tops of bearers to a consistent level, unless a designed fall is specified. Confirm straightness with a string line and pack only with approved structural packers where allowed.

Stagger joints in built-up or joined bearers away from adjacent connection points unless specifically detailed otherwise. Ensure adequate bearing at supports and maintain edge distances for bolts.

For wider decks, verify parallelism between bearer lines so joist spans remain consistent across the frame.

πŸ’‘ If a bearer has a natural crown, install it with the crown up to reduce future sag.

Step 6: Install joists and rim members

6️⃣ Lay out joists at correct centres

Mark joist positions on bearers using the nominated spacing, commonly 450 mm or 600 mm centres, depending on decking type, board direction and load requirements. Composite or narrow decking boards often require tighter centres than standard timber decking.

Install joists with crowns up and keep the top edges flush. Fix joists to bearers using direct skew nailing, structural screws, joist hangers or proprietary framing connectors as specified.

Install rim joists/boundary joists to lock the frame together and maintain joist spacing. Check the overall frame for square again by measuring diagonals once the perimeter is fixed.

Where joists are lapped over internal bearers, maintain full bearing and consistent lap lengths. Avoid introducing twist into the frame by forcing bowed members into place without restraint.

Step 7: Noggings, blocking and lateral restraint

7️⃣ Stiffen the subframe

Install noggings or solid blocking between joists where required to control twist, distribute load and improve frame rigidity. Spacing and arrangement should suit joist depth and overall deck geometry.

For elevated decks, install diagonal bracing or other lateral restraint measures to meet engineering and serviceability requirements. This may include:

Timber knee bracing
Steel strap bracing
Cross-bracing between posts
Additional anchor detailing at the building interface

Confirm that the subframe is rigid with no visible sway or roll before decking commences.

πŸ’‘ Elevated decks often fail in serviceability before ultimate strength. Lateral movement complaints usually come back to inadequate bracing, not undersized joists.

Step 8: Check fixings, corrosion protection and treatment

8️⃣ Finalise all structural connections

Inspect every structural fixing before proceeding:

Bolts fully tightened
Washers fitted
Joist hangers fully nailed or screwed to manufacturer schedule
Brackets installed with compatible fasteners only
No mixed metals likely to cause galvanic corrosion

In external applications, use hot-dip galvanised hardware as a minimum, and upgrade to stainless steel in severe coastal or poolside environments. Recoat all field cuts, notches and drill penetrations in treated timber.

Ensure any interface with masonry, steel or existing building fabric includes appropriate separation or flashing where required.

Step 9: Final level, line and square check

9️⃣ QA the completed substructure

Before decking boards are laid, complete a final quality assurance check:

Bearers level and straight
Joists at consistent centres
Frame square
Subframe dimensions match plan
No protruding fixings or split members
Bracing complete
All posts plumb
Clearance from ground adequate for ventilation and durability

Check drainage under the deck and ensure no timber is in unintended ground contact unless specifically rated for it. Confirm termite management provisions remain intact and visible where required.

A well-finished subframe should allow decking installation without requiring corrective packing, excessive planing or forced board alignment.

Common Mistakes to Avoid

1.Incorrect set-out from the start

Misread offsets, unsquared profiles or poor datum transfer create ongoing framing issues that are difficult to correct later.

2.Undersized members or excessive spans

Using 90x45, 140x45 or 190x45 members outside allowable spans leads to bounce, sag and non-compliance.

3.Poor footing placement and height control

Inaccurate footing locations or inconsistent stump heights result in excessive packing and out-of-level bearers.

4.Using the wrong hardware for exposure conditions

Standard zinc-plated fixings are not suitable for external structural framing, treated pine contact or coastal environments.

5.Insufficient bracing on elevated decks

Even when vertical loads are covered, lack of lateral restraint can produce frame movement and serviceability failures.

Pro Tips

πŸ’‘ Pre-mark all bearer and joist centrelines on your profiles before excavation so footing placement stays aligned with the framing layout.
πŸ’‘ Select straight framing timber early and allocate bowed members to shorter cuts, noggings or non-critical sections.
πŸ’‘ Keep joist crowns consistent by sighting each member before installation; mixed crowns create a wavy decking surface.
πŸ’‘ Use stainless steel fixings around pools, coastal sites and high-corrosion environments even if galvanised is technically acceptable.
πŸ’‘ Leave adequate subfloor ventilation and drainage under low decks to improve long-term durability and reduce cupping and decay risk.

Recommended Tools

Bosch GRL 300 HVG Rotary Laser Level β€” reliable for deck datum, footing heights and bearer level control
Makita 18V Brushless Impact Driver β€” suitable for structural screws, framing hardware and general deck framing work
Paslode Impulse Framing Nailer β€” efficient for timber framing assembly where nail fixing is specified
DeWalt 184 mm Circular Saw β€” practical for cutting 90x45, 140x45 and general framing members accurately
Sutton Blue-Metal Auger Bit Set β€” useful for clean drilling through posts and bearers for M12 bolt installations

Frequently asked questions

What is involved in frame a timber deck substructure?
πŸͺš Framing a Timber Deck Substructure A properly framed deck substructure is the backbone of a durable, compliant and straight-finished deck. For Australian residential work, the critical requirements are accurate set-out, correct footing and stump installation, appropriate bearer and joist si
What skill level do I need for frame a timber deck substructure?
Intermediate to Advanced β€” Estimated time: 1-3 days depending on deck size, footing type, access and site conditions
What are common mistakes when frame a timber deck substructure?
1. Incorrect set-out from the start Misread offsets, unsquared profiles or poor datum transfer create ongoing framing issues that are difficult to correct later. 2. Undersized members or excessive spans Using 90x45, 140x45 or 190x45 members outside allowable spans leads to bounce, sag and non-compliance. 3. Poor footing placement and height control Inaccura
What tools do I need for frame a timber deck substructure?
This guide includes a comprehensive tools list. Key carpentry & joinery tools are detailed in the Tools Required section.
What is the Australian standard for timber deck construction?
The primary Australian standard for timber deck construction is AS 1684 Residential Timber-Framed Construction. This standard outlines requirements for timber species, sizing, spans, and fixing methods to ensure structural integrity and compliance. Tradies must also consider the National Construction Code (NCC) and local council regulations.
How do I ensure my deck substructure is compliant with Australian regulations?
To ensure compliance, always refer to AS 1684, the National Construction Code (NCC), and local council building codes. Engage a structural engineer for complex designs or non-standard applications. Proper documentation, including engineering plans and material specifications, is crucial for obtaining necessary approvals and inspections.
What is the difference between H3 and H4 treated pine for deck substructures?
H3 treated pine is suitable for above-ground applications exposed to weather, offering protection against moderate decay and insect attack. H4 treated pine is designed for in-ground contact or severe weather exposure, providing enhanced protection against decay and termites. For stumps in direct ground contact, H4 or H5 is typically required.
What are common mistakes when framing a timber deck substructure?
Common mistakes include incorrect set-out, undersizing members for spans, and poor footing placement. Using the wrong timber treatment for exposure conditions, inadequate fixing, and neglecting proper drainage are also frequent issues. These errors can lead to structural failure, premature decay, and non-compliance with Australian standards.

Written by Chippy, the Carpentry & Joinery specialist at Aus.Tools.