Timber deck build cost in Northern Territory
A timber deck build in Northern Territory typically costs $8,070–$17,130 ex GST for 20 m², most likely about $11,760. Labour is about 42% of the price (49.9 hours). The range uses the award minimum of $29.45/hr from 1 July 2026, regional cost factors and a contingency band. Price data last updated 2 October 2026.
Updated
| Cost line | Low | Likely | High |
|---|---|---|---|
| Materials (20 m² + 10% waste) | $3,080 | $4,620 | $7,040 |
| Labour (49.9 hrs, crew of 2) | $3,840 | $4,940 | $6,310 |
| Footings & concrete | $390 | $660 | $1,100 |
| Waste removal | $170 | $280 | $440 |
| Contingency (8–15%) | $600 | $1,260 | $2,230 |
| Total (ex GST) | $8,070 | $11,760 | $17,130 |
Region: Northern Territory (regional factor ×1.10 on labour and site costs). About 3.5 working days on site. GST on the likely figure is about $1,180.
Included
- Treated pine sub-frame on concrete footings
- Hardwood or merbau decking boards
- Stainless or galvanised fixings
- One coat of decking oil
Not included
- Council / certifier fees
- Balustrades and stairs over 1 m
- Roofing or pergola
- Engineering for elevated decks
Common questions
- How much does a timber deck build cost in Northern Territory?
- For 20 m² on a typical site, the Price Card puts it at $8,070–$17,130 ex GST, most likely around $11,760. Change the size, crew, access and condition to see your own range.
- What is included in the range?
- Treated pine sub-frame on concrete footings; Hardwood or merbau decking boards; Stainless or galvanised fixings; One coat of decking oil. Materials include 10% waste, labour is priced by hours for the size and crew, plus site costs and a contingency band.
- How much of a timber deck build price is labour?
- Trades are mostly time. On this job labour is about 42% of the likely price (49.9 hours). A charge-out rate is not a wage: the award minimum for a qualified tradesperson is $29.45/hr from 1 July 2026, and super, leave, insurance, vehicle, tools, unbillable time and margin take it to roughly $74–$133/hr (our estimate).
- What is not included?
- Council / certifier fees; Balustrades and stairs over 1 m; Roofing or pergola; Engineering for elevated decks. Always confirm with a written quote.
- Is this a quote?
- No. It is an indicative planning range built from network benchmarks. We show how many real job outcomes have been reported for each job and state. Prices vary by site, supplier and season.
Sources
- Fair Work Commission: Annual Wage Review 2025–26 decision (1 Jul 2026): Award minimum rates up 4.75%; National Minimum Wage $1,004.90/week ($26.44/hr)
- Fair Work Ombudsman: Building and Construction General On-site Award (MA000020) (1 Jul 2026): CW/ECW 3 (tradesperson) $1,119.10/week, $29.45/hr minimum
- hipages: How much does a carpenter cost? (25 Aug 2026): Carpenters typically $40–$120 per hour
Price this job in another state
See every priced job and how a fair charge-out rate is built