Timber deck build cost in Queensland
A timber deck build in Queensland typically costs $7,550–$16,140 ex GST for 20 m², most likely about $11,040. Labour is about 40% of the price (49.9 hours). The range uses the award minimum of $29.45/hr from 1 July 2026, regional cost factors and a contingency band. Price data last updated 2 October 2026.
Updated
| Cost line | Low | Likely | High |
|---|---|---|---|
| Materials (20 m² + 10% waste) | $3,080 | $4,620 | $7,040 |
| Labour (49.9 hrs, crew of 2) | $3,420 | $4,400 | $5,630 |
| Footings & concrete | $340 | $590 | $980 |
| Waste removal | $150 | $250 | $390 |
| Contingency (8–15%) | $560 | $1,180 | $2,110 |
| Total (ex GST) | $7,550 | $11,040 | $16,140 |
Region: Queensland (regional factor ×0.98 on labour and site costs). About 3.5 working days on site. GST on the likely figure is about $1,100.
Included
- Treated pine sub-frame on concrete footings
- Hardwood or merbau decking boards
- Stainless or galvanised fixings
- One coat of decking oil
Not included
- Council / certifier fees
- Balustrades and stairs over 1 m
- Roofing or pergola
- Engineering for elevated decks
Common questions
- How much does a timber deck build cost in Queensland?
- For 20 m² on a typical site, the Price Card puts it at $7,550–$16,140 ex GST, most likely around $11,040. Change the size, crew, access and condition to see your own range.
- What is included in the range?
- Treated pine sub-frame on concrete footings; Hardwood or merbau decking boards; Stainless or galvanised fixings; One coat of decking oil. Materials include 10% waste, labour is priced by hours for the size and crew, plus site costs and a contingency band.
- How much of a timber deck build price is labour?
- Trades are mostly time. On this job labour is about 40% of the likely price (49.9 hours). A charge-out rate is not a wage: the award minimum for a qualified tradesperson is $29.45/hr from 1 July 2026, and super, leave, insurance, vehicle, tools, unbillable time and margin take it to roughly $74–$133/hr (our estimate).
- What is not included?
- Council / certifier fees; Balustrades and stairs over 1 m; Roofing or pergola; Engineering for elevated decks. Always confirm with a written quote.
- Is this a quote?
- No. It is an indicative planning range built from network benchmarks. We show how many real job outcomes have been reported for each job and state. Prices vary by site, supplier and season.
Sources
- Fair Work Commission: Annual Wage Review 2025–26 decision (1 Jul 2026): Award minimum rates up 4.75%; National Minimum Wage $1,004.90/week ($26.44/hr)
- Fair Work Ombudsman: Building and Construction General On-site Award (MA000020) (1 Jul 2026): CW/ECW 3 (tradesperson) $1,119.10/week, $29.45/hr minimum
- hipages: How much does a carpenter cost? (25 Aug 2026): Carpenters typically $40–$120 per hour